Content |
Target Function |
Overview |
|---|---|---|---|
|
1 |
New Feature |
Reports |
Reports can now be downloaded in CSV format. Report data can be used more convenient now. Reports can now be downloaded in CSV format
<Description> The contents displayed in PDF reports can now be downloaded in CSV format. Report data can now be easily utilized. *Multiple CSV files are downloaded as a Zip file.
|
|
2 |
New Feature |
Data layer |
Orthophoto registered in WGS84 can now be converted to the projects Coordinate System and Downloaded. Step1 press “Generate source files with site coordinate system”
Step2 after generating has completed and turned White again Press “Download source files (site coordinate system)” & the download will begin.
|
|
3 |
New Feature |
Data layer |
Survey data registered in DTM/DSM format can now be downloaded after conversion to the coordinate system set for the project. |
|
4 |
New Feature |
Measurements |
When calculating soil volume, the bulking factor and compaction factor can now be set for Cut and Fill respectively. The bulking factor and compaction factor can now be set for soil volume calculations.
<Description> When using the “Measurement” feature to calculate soil volume, it is now possible to set the bulking factor and compaction factor for soil volume calculation, respectively.
|
|
5 |
New Feature |
Project |
Advance Deployment As of today, this feature is only for Smart Construction Dashboard apps. When creating a new project on the dashboard, if the selected job site already has localization information, the project can now be created using that information. |
|
6 |
Enhancement |
PDF Report |
Update the Report issuing User Interface to one menu (PDF, CSV) |
|
7 |
Enhancement |
PDF Report |
Improved functionality to show totals in the tables of the stockpile report. |
|
8 |
Enhancement |
Machine connection |
When changing the allotment period of machine, the end date has been changed as required. |
|
9 |
Bug fix |
Data layer |
The status of a registered As-built became sometimes in the process even though no action had been taken. This problem has been corrected so that the status is not changed unexpectedly. |
|
10 |
Bug fix |
Project file |
Downloading of small files from Project file feature sometimes failed. Fixed so that they could be downloaded correctly. |
|
11 |
Bug fix |
File transfer |
In e-mails sent during file transfers, the name of the file being sent was sometimes displayed incorrectly. This has been corrected so that they are displayed properly. |
|
12 |
Bug fix |
Project |
When creating a project, a gc3 file containing a comma in the name of the control point could not be used to create the project. This issue has been corrected so that they are registered correctly. |